Summary
Video inspection found the Leeds/Main Street drainage needs complete replacement, pushing costs up. Federal grant money is capped at $2 million, so the extra comes from the county — likely from highway fund balance — with bids out by fall and construction still set for 2027.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jun 8, 2026.
Impact analysis
Unknown additional cost on top of the county's $500,000 local share of the $2.5 million project.
Leeds and Catskill get fixed drainage and a rebuilt Main Street by the end of 2027.
County taxpayers absorb the cost overruns beyond the capped federal grant.
Mentions & discussions (1)
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Greene County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.